RL30411: Electricity Restructuring and Tax-Exempt
Bonds:
Economic Analysis of Legislative Proposals
Dennis Zimmerman
Analyst in Public Finance
Domestic Social Policy Division
January 20, 2000
CONTENTS
List of Tables
Table 1. Can New Public Power Electric
Output Facilities Be Financed with Tax-Exempt Bonds?: Comparison of Economic Treatment
with Three Legislative Proposals
Table 2. Do Private-Activity Bond Rules Apply to Outstanding Bonds That
Financed Public Power's Existing Electric Output Facilities?: Comparison of Economic
Treatment with Three Legislative Proposals
Summary
Tax-exempt bonds reduce public power's interest cost on debt
and enable it to lower the price of electricity. This subsidy makes taxpayers better off
only if the private market fails to provide the correct amount of electricity. In general,
the private market can provide the correct amount of electricity; in those cases when it
can not, the tax-exempt bond subsidy is unlikely to correct the problem. Tax-exempt bond
legislation has been consistent with this perspective that an interest subsidy for
electricity production does not correct a market failure; its focus has been to prohibit
the spread of subsidized public power beyond its traditional service areas.
For public power entities entering a restructured and
competitive electricity network, the existing tax rules would eliminate tax-exempt status
for bonds that fund new capital facilities and also would require issuance of taxable debt
to retire outstanding tax-exempt bonds for existing facilities. As a result, several bills
have been introduced to change the current tax treatment of public power's debt after
restructuring occurs.
The analysis in this report suggests that general economic
welfare would be enhanced by enforcing the existing tax rules that would prohibit
tax-exempt bonds to finance new capital facilities used in the
competitive network. In contrast, it finds that economic welfare would be worsened by
enforcing the tax rules that would require bonds for existing facilities
used in the competitive network to be refinanced with taxable debt. Failure to grandfather
existing tax-exempt bonds could adversely affect economic gains from restructuring if the
expense of taxable interest rates induced public power to avoid the expense by maintaining
their monopoly (not participating in open access plans), thereby reducing the scope of
competition.
Some argue that the treatment suggested above might be
acceptable for generation facilities, but that a special exception should be made to allow
continued tax-exempt financing of new transmission and distribution facilities because
these facilities are similar to public highways. High exclusion costs make public
provision of local highways more efficient than private provision. However, exclusion is
not a problem for the transmission network. Continued subsidy via tax-exempt bonds would
lower electricity prices and reduce federal revenue without providing many offsetting
benefits for federal taxpayers. Distribution facilities might still be financed with
tax-exempt bonds for practical reasons, provided the facilities are also used to provide
other public services, such as street lighting.
The Administration's proposal, introduced by request as S. 1048, would institute
treatment fairly close to the economic treatment described in this report: no tax-exempt
bonds for new facilities, except for distribution; existing bonds for facilities used in
the competitive network would retain their tax exempt status. S. 386/H.R. 721 would institute
treatment that is relatively favorable to public power's continued use of tax-exempt bond
financing. H.R. 1253
would institute treatment that is generally closer to economic treatment than is S. 386/H.R. 721, but more
favorable for continued public power use than is S. 1048.
I. Introduction
The electricity industry has long been characterized by
monopoly, that is, by firms with exclusive franchises to transmit and sell electricity to
consumers in predetermined areas. Regulatory policies are being implemented at the present
time to restructure the industry. These policies would replace a portion of this
monopolistic structure with competition among utilities for the generation and sale of
power, and would require that facilities to transmit power be made available to all
generators of power at nondiscriminatory prices. The intention is to lower electricity
prices, thereby enhancing economic welfare. This move to restructure the industry has
heightened policy concerns about several cost-reducing tax advantages that give local
governments or their duly designated power authorities ("public power") the
capacity to sell electricity at a price that does not reflect its real resource cost. This
price potentially is below the price charged by utilities owned by private investors
(investor owned, or "IOUs"), whose price presumably more closely reflects real
resource costs. Continuation of these subsidies could reduce the enhanced economic welfare
that restructuring is expected to provide.
One of these cost-reducing tax advantages, the exclusion from
a federal taxpayer's gross income of the interest income earned on state-local debt,
reduces public power's capital cost. Although the IOUs long objected to public power's use
of these "tax-exempt bonds," the subsidy was not particularly economically
threatening as long as the electricity market was characterized by monopoly. From the
IOUs' perspective, competition makes the cost advantage conveyed by public power's use of
tax-exempt bonds a more serious threat to their market share and financial success.
The Internal Revenue Code limits public power's ability to
use tax-exempt bonds to finance output property when some of the output will be used by
private individuals and businesses on a basis other than the basis on which the general
public uses the output. (1) No more
than 10% of the bond proceeds ($15 million maximum) can be used to build capacity for such
private use. These private-activity bond rules would require many public power entities
that choose or are forced to engage in competition to forego use of tax-exempt debt for
new output property (generation, transmission, and distribution facilities) and to
refinance debt for existing output property at taxable interest rates. IOUs believe these
private-activity bond tax rules are appropriate.
From public power's perspective, the use of tax-exempt bonds
is an historical and legal right, one that enables it to provide electric power at a price
that does not reflect real resource cost for good reason. Public power believes that any
violation of the existing tax-exempt bond rules that results from actions taken to comply
with restructuring policies is not one it has chosen but one being forced upon it. It
believes tax-exempt bond law should be adjusted to allow public power continued use of
these bonds. (2)
Section II of this report explains how competition is
expected to affect electricity prices and how the use of tax-exempt bonds can affect these
prices. Section III analyzes whether the economic goal of electricity restructuring is
better served by continuing or eliminating public power's use of tax-exempt bonds. The
analysis indicates this goal is furthered by: (1) denying use of tax-exempt bonds for new
output facilities; and (2) not requiring existing output facilities to replace outstanding
tax-exempt debt with taxable debt. Some argue that continued use of tax-exempt bonds for
new output facilities would be beneficial because the cost reduction satisfies some
federal policy goal that provides benefits to federal taxpayers other than lower
electricity prices. This issue is discussed in section IV. Section V discusses the
contention that new transmission facilities are a special case and that investment in such
new facilities should receive special consideration for continued tax-exempt bond
financing. Section VI uses these analyses to compare the potential economic effects of the
major legislative proposals that would change the tax-exempt bond rules for electric
output facilities: the Administration's proposed treatment of tax-exempt bonds as
presented in its electricity restructuring plan of March 25, 1998, introduced by request
as S. 1048 by Senator
Murkowski; S. 386 and H.R. 721, introduced by
Senator Gorton and Representative Hayworth; and H.R. 1253 introduced by
Representative English. Section VII provides a brief discussion of another cost-reducing
tax advantage the Internal Revenue Code provides to public power, exclusion of its income
from federal income taxation. H.R. 1253 includes a
provision that would impose the federal income tax on some public power utility income.
II. Deregulation
of Generation and Retailing: Electricity Prices and Tax-Exempt Bonds
This section explains the relationship between deregulation
(the introduction of competition into the generation and sale of electricity) and price;
and how the use of tax-exempt bonds can affect the price charged by a utility.
A. Competition and Electricity
Prices
The provision of electricity in the United States
historically has been divided among investor-owned utilities (IOUs), public power,
cooperatives, federal agencies ("federal power"), and independent power
producers. In 1996, the 2,000+ public power utilities produced about 8.6% of the nation's
utility-produced electric power. Because public power purchases electricity for resale
from IOUs and federal power, it accounts for about 14% of final electricity sales.
Provision of electricity involves four distinct functions:
generation -- the creation of electricity; transmission -- transportation of electricity
over long distances; distribution -- transportation of electricity from distribution
centers to consumers; and retailing -- the metering and billing of consumers. The industry
historically has been organized into firms with exclusive franchises to sell electricity
to consumers within a predetermined area. Many of these monopolies are vertically
integrated, which means that they perform some combination of these four functions. Not
all firms perform all functions. For example, some distribute and retail but buy
generation and transmission services from other firms.
Monopolies are regulated by the government to counteract
their tendency to sell too little output at higher than optimal prices. With electric
utilities, this regulation tends to focus on setting prices to ensure that producers
receive an "adequate" rate of return on capital. In other words, prices are set
to enable each utility to recover its prudently-incurred capital costs, even if the
production facilities built with the capital are inefficient and produce power that is
more costly than could be obtained from alternative sources.
Some have argued that two of the four functions, generation
and retailing, are not natural monopolies and can be transformed into competitive markets.
In a competitive electricity market, prices would reflect the marginal cost of electricity
generation (the additional cost of producing an additional unit of output). Generation
plants for which this price is insufficient to pay for average costs (total costs divided
by total output) would be replaced by plants whose costs were lower. Inefficient producers
would be driven from the market and electricity prices would decline for many consumers.
The Energy Department has estimated that consumer benefits could amount to $20 billion per
year and as much as $32 billion in 2010. (3)
The Public Utility Regulatory Policies Act of 1978
inadvertently laid the foundation for restructuring by opening the generation of
electricity to non-utility entrants. (4)
These new entrants along with the advent of new generating technology created a
cost-effective alternative to traditional generation, leading the Federal Energy
Regulatory Commission (FERC) to approve interstate wholesale sales based on market rates
rather than on the seller's costs incurred to generate and transmit the power. The Energy
Policy Act of 1992 introduced additional competition in the wholesale generation market.
Of course, the advantages of low-cost electricity generation
can be lost if competitors with high-cost electricity who also own the transmission lines
price transmission services in a noncompetitive fashion. Accordingly, FERC Orders 888 and
889, adopted in April 1996, provide for open access to the interstate transmission grid at
the wholesale level for all generators of electricity, which means transmission services
must be priced in a nondiscriminatory manner. FERC does not have the authority, however,
to mandate open access within a state -- access that is necessary to realize the full
benefits of retail competition. Many states have been implementing or studying retail
competition, and are considering open access plans for transmission facilities. (5)
B. Electricity Prices and
Tax-Exempt Bonds
Government occasionally intervenes in the market system of
prices by imposing taxes on the production of some goods and granting subsidies for the
production of other goods. The subsidized producer can offer a lower price and has a
competitive advantage over unsubsidized producers. Section 103 of the Internal Revenue
Code (the Code) excludes from gross income and federal income taxation the interest income
on bonds issued by public power. This lowers the interest rate on the bonds and reduces
public power's cost of capital. Public power and its customers value the capital resources
at the interest cost paid by public power. But the real value of the capital is measured
by its best alternative use; this value is measured by the higher interest cost paid on
taxable bonds.
In a world without competition, public power can use its
lower borrowing cost to do any combination of three things. (6) First, it can pass the subsidy through to its customers
in the form of lower prices. Second, it can charge a price consistent with no subsidy and
use the cost savings to provide related services such as low-income energy assistance or
preferential rates for rural customers. Or it can pass the subsidy through to the
political jurisdiction's general fund for tax relief and/or increased public services.
Third, it can operate inefficiently with high variable costs (such things as labor, fuel,
and transportation), providing neither lower prices nor tax relief/higher public services.
To the extent public power chooses the first of these options
and lowers price, public power's customers either are being induced by the low price to
consume more electricity than they otherwise would or they could have purchased (absent
monopoly) that electricity from another producer who was paying the full cost of capital
but managed to produce electricity more efficiently. In either case, the system may be
wasteful. With the advent of competition in electricity generation, IOUs argue this
subsidy will give public power a competitive advantage over IOUs and could inhibit the
market adjustments necessary to produce electricity at the least cost to society.
III. Tax-Exempt
Bonds for Output Facilities?
The economic effects of continuing tax-exempt bond use after
restructuring differ depending upon whether the bonds finance new or existing output
facilities.
A. New Output Facilities
In a competitive market, price is set equal to marginal cost,
the cost of producing an additional unit of output. A firm making a decision about
investing in new plant will not make the investment if its expected price and output are
not sufficient to cover all costs inclusive of fixed costs. Since the tax-exempt bond
subsidy reduces public power's fixed costs, it gives public power the potential to drive
the market price down to a level that would impose losses on IOUs. Thus, according to
economic analysis, IOUs are correct that continued public power use of tax-exempt bonds to
finance new facilities in a competitive market could provide public power with a price
advantage.
B. Existing Output Facilities
Will the tax-exempt bonds that public power used to finance
existing output property allow it to charge a lower price and gain an unfair advantage
when competing to sell power from those facilities? Money that was borrowed to construct
existing output facilities represents fixed costs. The interest cost on its debt is part
of these fixed costs. Public power must pay these costs, unless it goes bankrupt, whether
or not it maintains its production and customer base.
A public power utility will make pricing decisions to compete
against other utilities on the basis of its variable cost, items whose use varies with
production such as labor, fuel, and transportation. It will lower its price to retain or
attract customers provided the marginal revenue from that decision equals or exceeds its
variable cost. If its variable cost is high relative to its competitors' variable cost,
those competitors will drive price down to a level where the public power authority cannot
compete and it will lose market share. If its variable cost is low relative to its
competitors' variable cost, it will drive price down to a level where its competitors
cannot compete and it will increase market share. Note that the lower interest cost of
public power relative to IOUs does not affect this pricing decision on production from
existing output facilities and under competitive conditions will not provide an unfair
advantage to public power. (7)
If a decision to compete or a mandate to share its facilities
with private entities causes public power's tax-exempt bonds to violate the
private-activity bond rules, these bonds become retroactively taxable. (8) The way such a situation is likely to be handled is
either for the utility to issue taxable debt and use the bond proceeds to retire the
tax-exempt debt or to pay the Internal Revenue Service the lost federal tax revenue that
would result if the bonds were to remain tax-exempt. Such increased costs shift up the
firm's fixed costs and decrease its net income or increase its net loss, but they do not
affect its variable cost or its pricing decision. In other words, forcing public power to
refinance its existing tax-exempt debt as taxable debt will not change the competitive
relationship between public power and IOUs nor will it improve the ability of deregulation
to provide economic benefits to consumers.
Refinancing at taxable rates could, however, have some
negative consequences. The federal government is responsible for regulating interstate
commerce in electricity, but the regulatory task for intrastate commerce is left to the
states. The federal government cannot force the states to force public power to open
access to its transmission and distribution facilities for intrastate retail competition.
Public power firms that see few benefits from competition may be reluctant to participate
in open access plans because the decision might cause their outstanding tax-exempt bonds
to become taxable and raise their interest costs. This would reduce the geographic reach
of the network, the amount of competition, and the potential benefits for other consumers.
Thus, it makes economic sense to provide public power relief
from post-restructuring violation of the private-activity bond rules for debt outstanding
at the time restructuring occurs. Providing relief would not adversely affect IOUs'
ability to compete for customers and the potential economic benefits of deregulation. A
decision to enforce the private-activity bond rules for existing output facilities has two
major consequences, one a clearly undesirable negative effect on economic efficiency and
the other a distributional effect whose desirability depends upon subjective judgments.
First, enforcing the existing rules might induce some public power authorities to refuse
to participate in open access plans in order to retain their tax-exempt bond privilege, an
action that would limit the scope of competition and reduce the economic gains from
restructuring. Second, for those public power authorities that do choose to participate,
it would shift the incidence of the cost of the subsidy from all federal taxpayers to
public power's electricity consumers.
IV. Might Social
Benefits Justify Post-Restructuring Tax-Exempt Bond Use for New Output Facilities?
Some argue that continued public power use of tax-exempt
bonds for new output facilities is a desirable public policy because this subsidy of
public power satisfies some federal policy goal that provides benefits to federal
taxpayers. Public power claims that its tax advantages flow from: (1) the right of
communities to operate electric utilities as a public service, the very basis of our
democratic and multi-level (federal) system of government; and (2) that its lower rates
relative to IOUs serve as a competitive yardstick that reflects the "true" costs
of electric service. (9)
A. The Justification for the
Tax Advantage
The alleged right of state-local governments to make their
own fiscal decisions in our democratic multi-level system of government without
interference from another level of government is a legal justification. It asserts that
any taxation of interest income derived from state-local bonds is unconstitutional because
the exemption is protected by the Tenth Amendment and the doctrine of intergovernmental
tax immunity.
As the congressional effort begun in 1968 to restrict
state-local governments' use of tax-exempt bonds for what Congress believed to be private
purposes intensified in the 1980s, the issue of whether the basis for tax-exempt bonds is
constitutional or statutory was tested in the courts. The issue was settled by a 1988
Supreme Court decision (South Carolina v. Baker, 485 U.S. 505 [1988]) that
rejected this claim of constitutional protection, leaving Congress free to impose
restrictions through the legislative process (described in detail in Section IV. B.). (10)
This Supreme Court decision leaves public power's second
argument to justify its use of tax-exempt bonds for new output facilities -- that its
lower electric rates serve as a competitive yardstick which reflects the true cost of
electric service. Section II.B. explained the economic perspective that use of tax-exempt
bonds allows public power to charge a price that understates the real resource cost of
electricity. This understatement of real resource cost can only represent what public
power refers to as "true" cost if the private market for electricity fails to
provide the proper amount of electricity at the proper price, and the tax-exempt bond
subsidy enables public power to lower its price and correct this market failure.
Markets can fail in a variety of ways. If electricity's
economic characteristics rendered it unsuitable for private production, public power
provision would be necessary. This is not the case. Electricity possesses the
characteristics required for private sector production: consumption can be denied to those
unwilling to pay for it (unlike national defense); and one family's consumption of a unit
of electricity prevents another family from consuming the same unit (again, unlike
national defense). Public production is not necessary in order that electricity be
provided, as is obvious from the fact that more than 75% of electricity consumption is
provided by IOUs.
But private markets also fail when they provide a good but
the amount they provide is too large or too small. In fact, this is the economic rationale
for state-local provision of many services. And it is the economic rationale (as opposed
to the legal rationale discussed above) for the tax-exempt bond subsidy of public capital
formation -- that state-local public capital facilities and the public services provided
by those capital facilities tend to be underprovided. The sheer number of state and local
jurisdictions implies that any one jurisdiction's political boundaries likely fail to
encompass all individuals and businesses who benefit from its public services. Thus, some
of the collective consumption benefits from public services spill over the border of a
taxing jurisdiction, as in the case of some educational services or environmental
projects. Collective consumption benefits from providing such goods exceed the benefits to
taxpayers in the providing jurisdiction. Because taxpayers tend to be unwilling to pay for
services received by nonresidents, it may be desirable for a higher level of government
(which does receive payments from the nonresident beneficiaries) to subsidize residents'
consumption in order to induce state-local governments to provide the proper, that is, a
larger, amount of facilities.
Thus, the economic case for a federal subsidy such as
tax-exempt bonds focuses on the likelihood that the state-local sector does not adequately
correct the private market failure, and this state-local "under provision" is
attributable to its citizens' unwillingness to pay for benefits that would be provided to
taxpayers living outside the jurisdiction. Does state-local provision of electricity
satisfy this criterion? Does the tax-exempt bond subsidy enable public power to account
for the social benefits and social costs of electricity?
Three circumstances might cause the amount of electricity
provided by public power to be nonoptimal and impose external or spillover effects on
nonresident federal taxpayers. First, the electricity production process might generate
environmental costs that flow down river or are carried upwind/downwind to nonresidents,
and consequently are not taken into account when making decisions about output and price.
To the extent these costs exist, from an economic perspective a more appropriate federal
response would be to impose a tax (thereby internalizing the pollution costs) or to impose
regulations, not to provide a subsidy to public power.
Second, reliance on a sole provider for a geographic area (as
a cost-minimizing strategy) might impose higher electricity costs and prices on
nonresidents by denying the utilities serving these nonresidents access to markets
necessary to achieve an efficient scale of operation. A subsidy of public power does not
correct this problem. In fact, the current efforts of the federal government and some
states to adjust the industry's regulatory structure to promote competition are designed
to correct this problem, and the tax-exempt bond subsidy of public power is potentially an
impediment to these efforts.
Finally, the development of public power may have been
necessary because private producers did not find it profitable to provide the universal
service that society deems to be fair at a cost that is affordable to geographically
isolated consumers. And federal taxpayers may value the redistributional aspects of such
service such that they are willing to pay for it. At the end of the 20th
century, universal service is a reality. (11)
But economists argue that using tax-exempt bonds to achieve such service is inefficient
and inequitable. Bond finance subsidizes consumers within public power service areas that
have no universal service problem. In areas with a problem, it subsidizes all consumers
rather than the relatively few who need it. In areas served by IOUs, bond finance provides
no subsidy for needy consumers. And finally, the federal government's Low-Income Home
Energy Assistance Program already provides such financial support in the form of grants
provided to the states to be used for low-income energy consumers.
In summary, the exclusion from federal income taxation of
interest income on tax-exempt bonds for public power is a subsidy that obscures rather
than reveals the true cost of electricity and redistributes income to public power
customers from the 75 percent of the country that purchases its electric power through the
private sector. Such subsidies might be expected to serve an efficiency goal of correcting
for market failure caused by spillover effects, but these do not appear to be great for
electricity provision, and those that do exist can be addressed through government
regulation or taxation of private industry rather than government production. To the
extent the subsidy is used to finance lower-cost service to those in need, such assistance
could probably be provided more efficiently (at lower federal budget cost) by an expansion
of the Low-Income Home Energy Assistance Program.
Of course, the subjective judgment of taxpayers in a state or
a local region still may be that public production of electricity is justified, and if
they believe such provision should be subsidized they are free to provide such subsidies
even in the absence of a federal subsidy. (12)
In addition to the benefits such a subsidy would provide to state-local taxpayers due to a
perceived correction of market failure, it would redistribute income to state-local
citizens according to each person's electricity consumption and from state-local citizens
according to each person's state-local tax burden.
B. Bond Legislation Affecting
Public Power
The preceding discussion suggests continued use of tax-exempt
bonds to finance new output facilities would tend to reduce the Nation's economic welfare.
Would denying such bond use represent a break with congressional tax-exempt bond policy?
Congress has engaged in a 30-year effort to deny use of the
federal subsidy provided by tax-exempt bonds for goods and services that do not satisfy
its conception of public services. (13)
And some of these efforts have been directed specifically at public power.
Having federal taxpayers pay part of the interest costs on
state-local borrowing encourages state-local governments to invest in capital facilities
to provide public services. But it also creates a problem: it encourages state-local
officials to use the low-cost capital to provide services to their constituents at a
reduced price, services that can be and are provided by the private sector at a higher
price that reflects the private sector's higher borrowing cost (the full value of the
resources used). The public sector can provide these services in two ways. First, it can
directly produce the good at a lower price. Second, it can make loans to private
businesses or private individuals to produce the good at a lower price. The potential for
the state-local sector to expand the scope of its production activities or to assume the
role of a commercial banker is obvious.
Congress first attempted in 1968 to control the commercial
banker role of state-local officials. It declared state-local bonds to be taxable if: (1)
25% or more of the bond proceeds are to be used by a nongovernmental person (the
"use" test); and (2) 25% or more of the debt service on the
bonds is to be secured (paid) by property used directly or indirectly in a trade or
business (the "security" test). These percentages were changed to 10% in the Tax
Reform Act of 1986, and bonds satisfying the tests were called taxable private-activity
bonds. (14)
The focus of these rules was to prevent tax-exempt bond
proceeds from being converted into loans for private investments in manufacturing and
commercial physical capital. Some activities were allowed continued use of tax-exempt
bonds even if they satisfied the private-activity bond rules. One of these activities is
"local furnishing" of electricity. An IOU's (or independent power producer's)
electricity sales must be confined to two contiguous counties or a city and a contiguous
county to qualify as a local furnisher eligible to use tax-exempt private-activity bonds.
However, Congress limited the use of these bonds by including them in the state
private-activity bond volume cap that is equal to the greater of $50 per state resident or
$150 million each year. Inclusion in the cap means that the bonds issued for local
furnishers must compete with most other exempt private activities within a state for a
share of the state's annual allocation of tax-exempt private-activity bonds. (15)
But many state-local governments historically have subsidized
electricity for their citizens through publicly owned utilities, not by conveying the
subsidy to IOUs or independent power producers. These publicly owned facilities also have
the potential for allowing private businesses to garner the benefits of the tax exemption
for private use. Thus, rules were developed that required public power contracts for the
sale of electricity to private businesses to be executed at non-preferential rates and
with terms that did not otherwise transfer additional portions of the tax-exempt bond
benefits to a private business. Those contracts that did not meet these requirements would
be counted against the 10% rules. (16)
This is a confusing situation. As discussed in the preceding
section, electricity has all the characteristics of a private good. About 75% of all
electricity consumption in the United States is provided by the private, not the public,
sector. By its very nature, public power converts the federal tax-exempt bond subsidy to
private use. But the only portion of the subsidy considered by the private-activity bond
tests to be private use is that portion associated with contracts offered at preferential
rates not available to the general public. (17)
Not counting as private use those contracts issued by public
power at non-preferential rates to large users located beyond its traditional service area
conceivably could have led to the expansion of public power's market share at the expense
of IOUs. This has not happened because the binding constraint here is the private market,
not the tax law. Before investors will purchase the bonds used to build public power
output facilities, they must be reasonably certain the facilities will generate revenue
sufficient to pay the interest and principal on the bonds. Substantial expansion of
capacity directed to large users outside public power's traditional service area cannot
provide such assurances. The buyers' demand for electricity is subject to fluctuation with
the business cycle, and, being beyond public power's traditional service area, the buyers
have an alternative supplier. In addition, the public power entities are dependent upon
other utilities for transmission and distribution services beyond their traditional
service areas, and these other utilities might charge rates that prevent it from passing
much of the tax benefit through in lower prices.
Nonetheless, congressional concern with the spread of power
subsidized with tax-exempt bonds caused it in the 1986 Tax Reform Act to impose more
severe restrictions on private use of bond proceeds for output property than it did for
all other eligible private activities. Any bond issue for which 5% or more of the proceeds
are used to finance output facilities is limited to a maximum $15 million of private use.
Thus, any bond issue for which 10% private use (the standard for all other private
activities) would exceed $15 million in effect is limited to less than 10% private use if
the private use is electricity generation. In addition, the $15 million limit applies to
all outstanding bonds for the project, not to each individual bond issue as is true for
all other private activities. Given that electric facilities often cost hundreds of
millions of dollars, for most projects the $15 million limitation imposes a private use
share much smaller than 10%.
Congress deemed this special treatment necessary because
pre-1986 law permitted IOUs temporary use of more than 25% of multiple billion dollar
public power bond issues. This occurred because bonds could be issued to finance public
power facilities whose output for public power customers would not be needed until far in
the future. The determination of private use of electricity output in a given year from
these bond-financed facilities was calculated as a percentage of the expected electricity
production over the facilities' life, thus allowing sale of excess capacity to IOUs that
far exceeded the allowable 25% that prevailed from 1969 through 1986.
Congressional desire to limit the spread of electricity
subsidized by tax-exempt bonds was further demonstrated by two additional actions that
followed the 1986 act. First, the Omnibus Budget Reconciliation Act of 1987 adopted a
provision that treats as private-activity bonds subject to the volume cap any tax-exempt
bond issue for which 5% or more of the proceeds are used to acquire output property owned
by IOUs. (18) The only exceptions are
for public power to acquire property to provide service to an area currently served or an
annexed area contiguous to and not more than 10% of the area currently being served. Given
the size of the volume cap and the size of most power projects, this provision virtually
precludes expansion of public power's market share through this means.
Second, the Omnibus Budget Reconciliation Act of 1996 further
restricted IOU or independent power producer use of private-activity bonds for "local
furnishing" (discussed earlier in this Section) to service territories that were
using the bonds prior to January 1, 1997. In effect, those providers using the bonds at
that time were grandfathered; additional "local furnishers" were prohibited.
In summary, allowing tax-exempt bonds to be used for new
output facilities after deregulation of generation and retailing has been implemented
would give public power a competitive advantage over IOUs. It would increase the share of
the market in which consumers are paying a price that does not reflect power's real
resource cost. This would be desirable only if the electric power market is characterized
by a market failure that is corrected by public power's use of tax-exempt bonds. This does
not appear to be the case. Furthermore, three decades of tax legislation seems to have
been directed to controlling the spread of the tax-exempt bond subsidy to areas not served
historically by public power. Denying use of these bonds for new public power output
facilities that are used to participate in the competitive market would prevent
differential treatment of IOUs, minimize distortions in the electricity market, and
continue the thrust of long-term federal tax policy in this area.
V. Are
Transmission and Distribution Facilities a Special Case?
Because the transportation of electricity over long distances
is most economically performed by one provider, transmission facilities do not appear
currently to be a good candidate for competition. The potential for an unregulated owner
of such facilities to provide favorable rates for its own power has caused FERC in order
888 and some states to propose that all transmission facilities be placed in the hands of
an independent system operator (ISO). This operator would be responsible for maintaining a
system open to all generators of electricity for the transmission of their power at
nondiscriminatory rates, thereby encouraging maximum retail competition.
Some have argued that an ISO, whether organized as a private,
nonprofit, or public firm, will in effect be a public utility providing services to the
general public, much as a public highway. As such, it is argued that new transmission
facilities are a special case and should be financed with tax-exempt bonds, even though
privately owned facilities are not currently eligible for tax-exempt financing. (19)
In fact, the economic characteristics of the transmission
network are not analogous to those of a public highway. Why are highways most often
provided by the public sector? First, if they are not congested, an additional user can be
accommodated at virtually zero marginal cost, which implies a price incompatible with
private provision. Second, even if the highway is congested, it can be very costly to
exclude those who do not pay for the service, particularly on local highway networks. And
as a practical matter, it is inexpensive to price the service through a user charge such
as the gasoline tax. In effect, this brief discussion indicates private highway provision
in many circumstances might result in too little and unnecessarily costly service being
provided.
Transmission services are very different. They may or may not
be subject to congestion. But it is not expensive to exclude those who don't pay. Such
services can easily be provided by the private sector, as is evidenced by the fact that
these services currently are overwhelmingly provided by the private sector.
Any failure of privately owned transmission facilities to
provide the correct amount of services is due to it being a decreasing cost industry
conducive to monopoly provision. This problem can be corrected by regulation. Allowing
continued use of tax-exempt bonds would mean the customer would be paying less than the
real resource cost of transmission services, even though this reduced cost is not
correcting a market failure.
Providing a tax-exempt bond subsidy would give the ISO the
potential for under pricing transmission services and encouraging too much electricity
consumption. Or it might lead to inefficient management that incurs unnecessarily high
variable costs. Or it might be used to continue the funding of the numerous subsidies of
related activities that are financed from the existing regulatory system's monopoly rents.
However the ISO might use a tax-exempt bond subsidy, Congress might consider whether
taxpayers receive benefits commensurate with the federal tax dollars they forego because
of the bond subsidy.
Although transmission facilities often are placed on property
reserved solely for transmission of electricity, distribution facilities often share
property being used for other public utilities such as street lighting. Denying tax-exempt
bonds would raise difficult administrative questions about what share of the investment in
this shared property is devoted to electricity, which should receive no financing subsidy,
and street lighting, which appears to have the characteristics of a public good and
perhaps should receive a subsidy. One might think of the tax-exempt bond financing as
being for street lighting, and the incremental costs for distribution facilities as being
minimal. This decision to allow tax-exempt bond financing of new distribution facilities
probably has at least as much to do with the practical realities of local public services
as it does with the economic principles discussed earlier.
VI. Analysis of
Proposed Legislation
Numerous bills have been introduced that deal with
electricity restructuring. This report considers three bills that cover the spectrum of
proposed changes to tax-exempt bond law for electric output facilities: S. 1048 (Senator
Murkowski, introduced by request of the Administration); S. 386 (Senator Gorton) and
its companion H.R. 721
(Representative Hayworth); and H.R. 1253
(Representative English). The purpose here is to compare the treatment these three bills
would impose on tax-exempt bonds to the findings of the preceding economic analysis. The
information is organized in two tables. Table 1
asks: "Can New Public Power Electric Output Facilities Be Financed with Tax-Exempt
Bonds?" Table 2 asks: "Do
Private-Activity Bond Rules Apply to Outstanding Bonds That Financed Public Power's
Existing Electric Output Facilities?" These questions are addressed separately for
the three types of facilities: generation (G), transmission (T), and distribution (D).
A. Economic Treatment
The economic treatment developed in sections II through V of
this report is presented in the shaded column of both tables in order to highlight it as a
reference point to which the three legislative proposals are being compared. Table
1 indicates that were "Economic treatment" implemented, new generation
and transmission facilities would not be financed with tax-exempt bonds. This denial would
not depend upon whether any or all of these facilities are used in the competitive
network. Distribution facilities could be financed with tax-exempt bonds if the property
used to provide retail electric services is also used to provide other utility services
that possess public good characteristics, such as street lighting.
Table 1. Can
New Public Power Electric Output Facilities Be Financed with Tax-Exempt Bonds?:
Comparison of Economic Treatment with Three Legislative Proposals
Type of
Facilities |
Economic
Treatment |
S. 1048 |
S. 386
and H.R. 721 |
H.R. 1253 |
| Generation (G) |
NO |
NO |
YES; more private use permitted if T&D are open access |
NO is the general rule; YES if power sold only within local
service area, or utility services <5,000 customers and 30% of gross income is from
residential sales |
| Transmission (T) |
NO |
NO |
YES; unlimited private use if open access |
NO is the general rule; YES if the facilities are located in
local service area and satisfy criteria described for generation facilities |
| Distribution (D) |
YES, if shared with other public facilities |
YES |
YES; unlimited private use if open access |
YES if located in local service area; otherwise NO |
Table 2 indicates that were "Economic
treatment" implemented, outstanding bonds for existing output facilities would not be
subjected to the private-activity bond rules. This relief would not depend upon whether
the facilities are used in the competitive network.
B. Discussion of S. 1048
The Administration's "Comprehensive Electric Energy
Competition Plan" provides:
... that (1) private use limitations are inapplicable to
outstanding bonds for publicly-owned generation, transmission or distribution facilities
if used in connection with retail competition or open access transmission, and (2)
tax-exempt financing is unavailable for new generation or transmission facilities.
Tax-exempt financing would continue to be available for distribution facilities subject to
current law private use limitations. (20)
Table
2. Do Private-Activity Bond Rules Apply to Outstanding Bonds That Financed Public
Power's Existing Electric Output Facilities?: Comparison of Economic Treatment with Three
Legislative Proposals
Type of
Facilities |
Economic
Treatment |
S. 1048 |
S. 386
and H.R. 721 |
H.R. 1253 |
| Generation (G) |
NO |
NO, if facilities used in competitive network |
NO, if renounce use of tax-exempts for new generation
facilities; YES if don't renounce, with more private use permitted if T is open access |
YES |
| Transmission (T) |
NO |
NO, if open access |
NO, if T is open access; YES if not open access |
NO if T is open access; YES if not open access |
| Distribution (D) |
NO |
NO, if open access |
NO, if D is open access; YES if not open access |
NO if D is open access; YES if not open access |
The legislation that would make these changes, S. 1048, was introduced by
Senator Murkowski by request of the Administration. Table 1
shows that S. 1048
would deny tax-exempt bond financing to all new generation and transmission facilities.
The denial is universal; any bond issue for which any of the borrowed funds are used to
finance new electric generation or transmission facilities is a private-activity bond, and
therefore taxable. The denial does not depend upon whether the public power authority
joins the competitive network or decides to maintain its monopoly franchise.
This change would deny a competitive advantage that public
power could use to charge less than the full resource cost of its electricity. It would
enhance economic welfare by forcing electricity prices to more nearly approximate real
resource costs, or by denying use of the tax benefits to subsidize other state-local
services or to over compensate labor. And it would provide no incentive to keep public
power facilities out of the competitive network.
The proposed legislation would continue to allow use of
tax-exempt bonds for distribution facilities.
Table 2 shows that S. 1048 would allow
outstanding tax-exempt bonds that were used to finance existing electric output facilities
to remain tax exempt if they violate the private-activity bond rules, provided the
facilities are part of the competitive network. The economic analysis presented earlier
suggests the private-activity bond rules should be waived whether or not the facilities
are part of the competitive network.
C. Discussion of S. 386 and
H.R. 721
This proposed legislation would allow future transmission and
distribution facilities to be financed with tax-exempt bonds. As indicated in
Table 1, allowing new transmission facilities to be financed with tax-exempt debt
is not consistent with the economic analysis presented. It would allow transmission
services to be priced at a level that does not reflect full resource cost and could lead
to over consumption of transmission services. It could lead to inefficient production
decisions. High-cost (but subsidized) transmission facilities might be extended to satisfy
increased demand when it might be more efficient to use low-cost (but unsubsidized)
generation capacity from another source to satisfy this demand increase.
The exception for local distribution facilities is consistent
with the economic analysis and S. 1048's proposed
treatment, provided the facilities are also used to provide other public services, such as
street lighting.
Comparing the remainder of the bill's provisions to economic
treatment is complicated because the bill gives public power a choice about whether to use
tax-exempt bonds to finance future generation facilities, a choice that then affects the
treatment of outstanding tax-exempt bonds. The most direct way to present the results is
to describe each cell in the S.
386/H.R. 721
columns of Tables 1 and 2, and follow with more detail
about some of the provisions.
Table 1 shows that public power can elect to
continue using tax-exempt bonds for new generation facilities. If a utility's transmission
and distribution facilities provide open access to other electricity retailers, these
facilities would enjoy more private use than is currently permitted by the tax law. Of
course, as discussed earlier in this report, allowing these generation facilities to be
financed with tax-exempt debt gives a public power authority a competitive advantage in
pricing over the potential competitors for whom open access provides entrance to the
public power authority's market. Table 1 also
shows that, as noted at the beginning of this section, new transmission and distribution
facilities can be financed with tax-exempt bonds, and these facilities would enjoy
unlimited private use if they are open access facilities.
Table 2 shows that the application of the
private use rules depends upon whether the utility has chosen to renounce the use of
tax-exempt bonds for future generation facilities. If use of the bonds for generation
facilities is renounced, the private use rules do not apply to outstanding debt. If use of
the bonds is not renounced, the private use rules do apply, but more private use is
permitted for generation facilities if the utility's transmission facilities are open
access.
Table 2 also shows
that the private use rules do not apply to existing transmission and distribution
facilities if these facilities are open access. The private use rules do apply if the
facilities are not open access.
What is meant by the language "more private use
permitted" that appears in the S. 386/H.R. 721 column of
Tables 1 and 2? Section 2(a) of the bill would relax private use
restrictions for utilities that allow open access on its transmission or distribution
facilities. Sales on terms other than those available to the general public would not
count as private use if the sale is to an on-system purchaser. An on-system purchaser is
one who purchased output from the governmental unit some time during the 1996-98 period
and whose facilities are directly connected with the governmental unit's transmission or
distribution facilities. Sales on terms other than those available to the general public
would not count as private use if the sale is an existing off-system sale, provided open
access service is provided for transmission or distribution. An existing off-system sale
is one made to an entity that was an off-system purchaser some time during the 1996-98
period, and for which the sale does not exceed the pre-adoption purchase of kilowatt
hours.
Thus, the permissible private use of generation facilities
would increase because existing on-system and off-system sales would not count against the
limits. Only new sales would count as private use. Thus, the capacity for private use
would be increased.
The election to renounce future use of tax-exempt bonds for
generation facilities is limited only to bonds issued for electric facilities. It does not
apply to:
- bonds that "qualify" for other exempt private
activities, such as solid waste disposal;
- refunding bonds that meet the requirements of current law;
- transmission and distribution facilities in service on the
date of enactment;
- pollution control facilities for output facilities in service
on the date of enactment;
- repair of facilities in service on the date of enactment.
To the extent these various facilities are in competition
with IOUs, the bond subsidy would enter into the pricing decision and would provide a
competitive advantage for public power. For example, some suggest that the repair
exception might be used to finance new turbines in a hydroelectric power plant, thus
extending its productive life for another 50 years. This would substitute tax-exempt debt
for what otherwise would have been a new facility financed with taxable debt.
D. Discussion of H.R. 1253
Section 1(b) of the bill classifies any public power bond
issued for the construction or acquisition of electric generation and transmission
facilities as private activity bonds, and therefore not eligible for tax-exempt status.
This is reflected in Table 1 as "NO is
general rule." This treatment is consistent with achieving the objectives of
electricity market restructuring.
Certain facilities placed in service after enactment of the
rule are excepted from this rule and would still be eligible for tax-exempt financing.
- facilities owned by "local government utilities"
that are located in the utility's service area (except for generation facilities that can
be located outside), sell services only to consumers located in the service area, and
which are not designed differently, sized larger, built sooner, or constructed in a more
costly manner than necessary to provide services to service-area consumers.
- the share of facilities a "local government utility"
owns in a Joint Action Power Agency.
- facilities owned by a "small governmental utility,"
which provides services to fewer than 5,000 consumers, and for which at least 30% of
average gross income in any 3-year period is from residential customers.
- local distribution facilities if located within the service
area.
These exceptions are reflected in Table
1 as "YES if ..." The requirement that consumers be located within
the utility's service area is waived if:
- the sales outside the service area are to another "local
governmental utility" for sale to its service-area customers; the sales represent
qualified pooling arrangements for which annual pooling sales do not exceed annual pooling
purchases;
- the sale is required by a binding contract in effect on the
date of enactment or if the contract renewal is at the option of the purchaser;
- the sale is to a utility for distribution through its
facilities and the value is de minimis, that is, it does not exceed 10% of the
selling utility's average de minimis-type sales in the preceding 3 years;
- the sale represents transmission or distribution services over
facilities placed in service prior to enactment of the bill, and any associated sales of
the utility's own electric power generation are to consumers within its own service area.
Most of these exceptions would maintain the tax preference
for facilities whose use is restricted to within the service area. If this induced public
power not to join the competitive network, consumers outside the area would be prevented
from benefitting from peak-load capacity in the public power system. In addition, the
tax-exempt bond subsidy can still be used to assist in keeping electricity prices low
within the service area, possibly leading to more consumption than would otherwise occur.
The exception for local distribution is consistent with
economic treatment if the facilities are also used to provide other public services, such
as street lighting.
Section 1(c) would eliminate private use rules for tax-exempt
bonds that were used to finance existing transmission and distribution facilities, if the
facilities provide open access to competitors. This is reflected in "NO if T (D) is
open access." This treatment is consistent with the economic welfare analysis above.
Tax-exempt bonds that were used to finance existing generation facilities would continue
to be subject to existing private use rules ("YES" in Table
2). This is not consistent with economic welfare; it would discourage public
power competition in circumstances where the tax preference does not provide public power
with a competitive advantage.
VII. H.R. 1253
and Federal Taxation of Public Power Income
H.R. 1253 includes one
additional provision that has nothing to do with tax-exempt bonds, but that nonetheless
has the potential to affect the relative competitive positions of public power and IOUs.
Section 115 of the Internal Revenue Code excludes from taxation the net income derived by
state and local governments from the operation of any public utility. (21) In effect, public power does not have to pay one of the
significant variable costs of electricity production. As a result, the choice of public
power versus IOU production of electricity is distorted in favor of public power.
H.R. 1253, alone among
these bills, would subject some government electric utility income to federal income
taxation. This taxation would apply only to income earned on sales outside its service
area, and exceptions would be made for sales that qualify for the "small government
utility" exception, the pooling exception, or the de minimis exception.
Nonetheless, removing the near-absolute protection Section 115 provides for government
business income would be consistent with economic welfare, since the income tax exemption
is a variable cost and would enter into the utility's pricing decision. It could, however,
raise major legal questions. Not taxing sales within the service area would likely lead to
a host of practical problems similar to those that arise in assigning income to domestic
and foreign sources for purposes of income taxation. The firm has a strong incentive to
assign its income to the jurisdiction with the lowest rate of taxation, thereby avoiding
some portion of its properly measured tax burden. Such practical problems could be avoided
if the tax were extended to sales within the service area.
Footnotes
1. (back)Private
use is not dependent upon whether the purchaser is located within the geographic area of
the power authority's governmental unit(s). Rather, it depends upon the nature of the
authority's contracts with the non-general-public purchasers. If contracts transfer the
benefits and burdens of the ownership of facilities financed with the tax-exempt bonds to
these purchasers, the contracts are considered to be made on terms other than those
available to the general public and thus constitute a private use. Such use might take the
form of a "take or pay" contract that requires the purchaser to pay for all
power specified in the contract, whether or not the power is used.
2. (back)American
Public Power Association, Public Power and the Myth of the Electric Utility Industry's
"Level Playing Field," undated. See p. 1-2.
3. (back)U.S.
Department of Energy. Supporting Analysis for the Comprehensive Electricity
Competition Act. DOE/PO-0059, May 1999.
4. (back)A
more complete discussion of legislation relevant to electric deregulation appears in CRS
Issue Brief IB10006, Electricity: The Road Toward Restructuring,
by Amy Abel and Larry Parker, updated October 1, 1999, 15p.; and CRS Electric Utility Restructuring Briefing Book
5. (back)
See Electric Utility Restructuring Briefing Book
for information about state-local policies.
6. (back)A
second cost advantage is provided by public power's exemption from paying federal income
taxes. Some argue that these public power federal tax benefits only work to offset federal
tax benefits received by IOUs. IOUs' tax benefits may reduce their effective tax rate on
net income below their statutory rate. However, unless this tax treatment reduces the
effective federal tax rate to zero, the cost advantage enjoyed by public power's exemption
from federal income taxation is reduced, but not eliminated.
7. (back)The
same cannot be said for two other federal cost advantages enjoyed by public power: (1)
exemption of its income from federal income tax; and (2) preferences for the purchase of
low-cost federal power. Both of these advantages do enter into variable cost and will
affect pricing decisions on output from existing facilities. For a discussion of federal
power preferences, see: CRS Report 95-356, Power Marketing Administrations: A Time for
Change?, by Larry Parker. (Archived).
8. (back)The
Joint Committee on Taxation has provided a variety of specific examples to illustrate how
such post-issuance violations might occur. Joint Committee on Taxation, Federal Income
Tax Issues Arising in Connection with Proposals to Restructure the Electric Power Industry,
(JCS-20-97), October 17, 1997, 18-20.
9. (back)American
Public Power Association, Public Power and the Myth of the Electric Utility Industry's
"Level Playing Field," undated. See p. 1-2. Washington, D.C.
10. (back)Few
issues are ever entirely resolved, and this one could arise again some time in the future.
Some argue the Supreme Court's South Carolina decision is incorrect on the basis that it
presumes the federal government has a property right to the interest income on tax-exempt
bonds. If this federal property right does not exist, the exemption cannot be equated to a
subsidy, and the economic argument justifying taxation of the interest income of
state-local debt is incorrect. "By way of illustration, one certainly would not label
the decision by a thief not to rob an owner a subsidy to the owner from the
criminal." Maxwell A. Miller and Mark A. Glick, "The Resurgence of Federalism:
The Case for Tax-Exempt Bonds," Texas Review of Law & Politics, v.1,
Spring 1997, 25-59.
11. (back)This
may be attributable in part to direct federal programs such as the Rural Utilities Service
and in part to the regulatory process subsidizing some service with monopoly rents. The
reduction in these monopoly rents is a byproduct of industry restructuring and could put
such subsidies at risk. The Administration's restructuring proposal would finance these
subsidies from a Public Benefits Fund financed with an excise tax on every electric bill.
12. (back)In
fact, public power does not pay state or local income taxes. In some cases, it does make
some smaller payments in lieu of state-local income taxes.
13. (back)For
more detail concerning the legislation discussed in this section, see CRS Report 96-698, Tax-exempt
Bond Legislation, 1968-1996: An Economic Perspective, by Dennis Zimmerman.
14. (back)The
most comprehensive discussion of legislative changes affecting public power appears in
Joint Committee on Taxation, Federal Income Tax Issues Arising in Connection with
Proposals to Restructure the Electric Power Industry, (JCS-20-97), October 17, 1997,
9-20.
15. (back)Additional
restrictions on local furnishers were enacted in 1996, discussed below.
16. (back)A
discussion of these contract rules is provided in Temporary and Proposed Private
Activity Bond Regulations: Public Utility Output Facilities, Fulbright & Jaworski
L.L.P., January 1998.
17. (back)This
internal inconsistency is inherent in the form of the subsidy, one that is provided to any
service state-local governments choose to provide. In the absence of constitutional
protection for tax-exempt bonds, Congress could choose to eliminate such inconsistencies
and many difficult tax-exempt bond policy issues by taxing the interest income on
state-local debt and providing an explicit subsidy to those state-local services it
believes provide significant economic benefits to federal taxpayers. Such a "taxable
bond option" has been considered by previous Congresses but not enacted. The Taxpayer
Relief Act of 1997 instituted Zone Academy Bonds, a variant of the taxable bond option
structured to provide a taxable federal tax credit rather than tax-exempt interest income.
These bonds, which effectively pay all of the state-local government's interest cost, are
restricted to certain capital facilities for education. See CRS Report 97-828, Tax-Exempt
Bond Provisions of the Taxpayer Relief Act of 1997, by Dennis Zimmerman.
18. (back)This
provision is discussed in CRS Report 88-174, Tax-exempt Bond Financed Takeover of
Investor-owned Utilities: An Issue of Privatization and Competition, by Dennis
Zimmerman. (Archived).
19. (back)Were
the ISO organized as a private firm, it would violate existing tax-exempt bond law and
could not use tax-exempt bonds. The fact that it could be organized as a private firm
essentially says that these services possess the characteristics of a private good and
public subsidy is only economically justified if the "correct" amount is not
provided.
20. (back)U.S.
Department of Energy, Comprehensive Electricity Competition Plan, March 25, 1998.
21. (back)Section
115 of the Internal Revenue Code excludes from taxation the gross income state and local
governments receive from the operation of utilities and the provision of other
"essential" services. The economic and legal aspects of taxing this income is
largely unexplored. See Moshe Schuldinger and Dennis Zimmerman, "Taxing State and
Local Government Production: Economic and Legal Perspectives," Nation Tax Journal,
v. 52, no. 3, September 1999 (forthcoming).
|